The installation process of ceramic structured packing can be carried out by referring to the following steps:

1. After opening the package, the package should be lifted into the tower according to the frame diagram and package label and the series number. During this process, it is strictly prohibited to deform the package or bring any dirt into it.
2. Porcelain corrugated packing shall be tied with brown rope according to the serial number in the tower, and then sent into the tower through the entrance hole. All packaging of Hengerwo Chemical can not be loosened in the installation process.
3. After the packing support frame is installed, its surface should be smooth and clean. When installing, it is necessary to ensure that the flatness error is within the specified range. For example, if the inner diameter of the tower D is ≥2m, the flatness error is not less than 4mm.
4. Starting from the port on the packing bracket, Hengerwo Chemical will mark the inner wall of the tower every meter to mark the number of meters, so as to grasp the position of the packing layer at any time.
5. The direction of each layer of packing and the orientation of the corrugated plate of the next layer of packing overlap with a 90-degree Angle of view. After each package enters the tower, it should be placed according to the series number.
6. The packing block should be packed closely without any gap. After each pad is in place, adjust the tightness of each place with a special packaging tool, and firmly step on each place. The bottom plate must be in close contact with the bottom plate.
7. Do not bring dirt in the packing installation link, and do not leave packing such as fine iron wire in the tower.
Please note that the above steps are for reference only, and the actual installation process of Hervo may vary depending on the specific situation. When installing ceramic structured packing, you are advised to refer to the related installation instructions and operating regulations to ensure safe and effective installation. At the same time, considering that packing installation may involve some professional operations and equipment, it is recommended to carry out under the guidance of professionals.